Anticipated work this week, June 21-25, 2021:
- All water services are expected to be complete by the end of this week. This should be the end of scheduled water service disruption to residents.
- Additional storm sewer improvements have been planned at the intersection of 6th Street and 2nd Avenue after discussion with City staff. This will take place on the east leg of the intersection. The 6th Street closure will be extended approximately 50 feet to the east, but this additional work is not expected to affect 6th Street residents any more than the current road closure.
- Grading and rocking of 6th Street from 2nd Avenue to A Avenue.
- Sidewalk paving on 9th and 11th Street.